April 2008 Building Project Update

April 2008 Timeline - English

The April 2008 Building Project Update is here!

April 2008 Update in PDF

Final construction drawings are nearly complete for the new "Worship Center." As you may recall, three floors will be constructed for an estimated total project cost of $11.6 to $12.8 million. The 3 floors include:

We will also be constructing an outdoor Plaza with more than 10,000 sq. ft. of space including covered walkways, water features, landscaping, benches, café tables and seating.

How much "new" Sanctuary, Classroom and Lobby space will be built?

Existing Sanctuary (including balcony) 5,000 sq. ft.
New Sanctuary (excl. future 3rd fl. balcony) 11,000 sq. ft.
New Classrooms 1,300 sq. ft.
Less Demolished Classrooms 3,300 sq. ft.
Net New Classroom Space 8,000 sq. ft.
Existing Lobby 700 sq. ft.
New Lobby & Lounge 4,300 sq. ft.

We are about 8 weeks away from mobilizing the construction crews and beginning the relocation of utilities and demolishing the office wing. The remaining project schedule is a follows:

April 14-25, 2008 Building exterior and site bidding phase
May 7, 2008 Final cost (80% of GMP) for building exterior and site improvements
May 9, 2008 Interior drawings completed
May 12-23, 2008 Interior bidding phase
May 17-18, 2008 Informational Meetings
May 30, 2008 Final cost (20% of GMP) for interior work
May 31-June 1, 2008 Informational Meetings
June 8, 2008 Congregational Meeting
The week of June 16 Construction mobilization
Doors open July-September 2009!

Questions? Please contact Dale Himes, Project Manager (503-804-8911), Scott Moore (503-643-6511) or any Staff, Elder Board and Communication team member. Also, visit www.radicalconnections.org and/or www.vbconline.org for Monthly Project Updates and Weekly Prayer Reminders.