September 2007 Building Project Update
Fast Facts
New Worship Center
- Approximately 130 x 170 ft = 32,500 sf
- To be located just north and adjacent to the existing Sanctuary and Gym
- Includes 800 seat Sanctuary, Lobby, Classroom & Support Space
Design Features — similar to Horizon Community Church, Tualatin
- Modular concrete tilt-up
- Expandable in the future
- Exposed roof trusses, HVAC & acoustical panels
New Sanctuary
- Approximately 100 x 130 ft = 13,000 sf
- Multi-use/flat floor
- 800 variable seating capacity — double existing sanctuary 1st floor capacity
- Emphasis on sound, lighting, art and media
- Upgrade sound and lighting in existing sanctuary
Lobby
- Approximately 30 x 130 ft = 3,900 sf
- Meeting & connecting courtyard area
- Refreshment bar
- Conversational seating
Classrooms & Support Space
- Approximately 40 x 130 ft x 3 floors = 15,600 sf
- Ground floor - childcare
- 1st floor - 3 or 4 classrooms
- 2nd floor - meeting room(s) & offices
Estimated Project Schedule
- Design begins - October 2007
- Groundbreaking - June-August 2008
- Occupy building - Summer 2009
- Project Duration - 21-23 months
Worship Center Funding Model
- $1.6M - Current in VFF
- $5.2M - Pledges Outstanding
- $4.8M-$6.0M - Bank Loan or Additional Contributions
- $11.6M-$12.8M Estimated Project Total
Estimated Decision Milestones
- Approval to Proceed - September 2007
- Schematic Design - January 2008
- Design Development - April 2008
- Construction Documents/Bid/GMP - May 2008
Questions? Please contact Dale Himes (503-804-8911), Scott Moore (503-643-6511) or visit www.radicalconnections.org for Monthly Project Updates.