Another good week last week as the sanctuary floor slab and 9 wall panels were poured. This week 6 more wall panels and a footing for the 2nd elevator in the existing building are scheduled to be poured.
Some dates to keep in mind: On Wednesday of Thanksgiving week, a 150 ft. boom crane is scheduled to arrive (in sections) and prepare for the tilt-up of the first 15 of 44 wall panels. The tilt-up of these wall panels will be in the lower level and will occur Monday, December 1st through Thursday, December 4th. Prepare to be amazed!