Weekly Prayer Reminder: 2-9-2009
- This week steel framing continues—focusing on the roof structure. Metal decking will also be laid out for the Main and 3rd floors. The Plaza is getting more attention as well as footing work continues on the steps and waterfall feature. Backfilling and compaction of soil in the Plaza area will also be taking place.
- Please pray for the safety of the steel crews as they walk the girders and move steel into position to be welded and bolted.
Dale Himes
Project Manager
Psalm 67:1