Now that we have begun construction, there will be six major work phases that need to be completed before our first service in the fall of 2009. I will be continually tracking our progress with new weekly construction activities shown in bold type. Please focus your prayers on the new upcoming work, obtaining permits and for safety of the construction crews:
- Demolition
- construction trailers arrive
- main electrical power relocation begins
- emergency service panels relocated
- office/classroom wing down to bare walls
- office portables removed
- main electrical power relocation continues
- natural gas main relocation begins
- asbestos abatement begins
- asbestos removal continues in the office/classroom building
- more separation walls constructed for demolition
- natural gas rerouting continues, new meter set, old one removed
- PGE sets new transformer and new wire is pulled
- plumbing is capped in the office/classroom building
- Rita driveway and new connecting pathways are paved
- Sitework
- New Building Shell
- Plaza
- Existing Building Improvements
- New Building Interior Improvements