This week work continues on installing the roof decking, staircase, plumbing, electrical, heating and fire sprinkler systems. Black weatherproofing sealant is also being "painted" on the alcoves and selected wall sections in preparation for the wood siding overlay. Rough flooring and framing will also continue on the new foyer addition to the existing sanctuary.
Question of the Week: Will the Worship Center have a baptismal, piano and organ? Yes, the new baptismal will be recessed in the stage. There will also be a new piano, organ and audio-visual system arriving and installed after the building is completed in June.
On Schedule for building completion in June and Grand Opening September 11-13, 2009;
On Budget at $11.6 million.
Dale Himes
Project Manager