Weekly Prayer Reminders: 4-14-2008

The clock is ticking and summer is nearly here. "Only 8 weeks to go before......" See below for this month's Building Project Update which will also be placed in this week's church bulletin. There is no shortage of things to pray about.

Final construction drawings are nearly complete for the new "Worship Center". As you may recall, three floors will be constructed for an estimated total project cost of $11.6 to $12.8 million. The 3 floors include:

We will also be constructing an outdoor Plaza with more than 10,000 square feet of space including covered walkways, water features, landscaping, benches, cafe tables and seating.

How much "new" Sanctuary, Classroom and Lobby space will be built?

Existing Sanctuary — including balcony 5,000 sq. ft.
New Sanctuary — excl. future 3rd fl. balcony 11,000 sq. ft.
New Classrooms 11,300 sq. ft.
Less Demolished Classrooms 3,300 sq. ft.
Net New Classroom Space 8,000 sq. ft.
Existing Lobby 700 sq. ft.
New Lobby & Lounge 4,300 sq. ft.

We are about 8 weeks away from mobilizing the construction crews and beginning the relocation of utilities and demolishing the office wing. The remaining project schedule is as follows:

Questions? Please contact Dale Himes, Project Manager, (503-804-8911), Scott Moore (503-643-6511) or any Staff, Elder Board and Communication team member. Also, visit www.radicalconnections.org and/or www.vbconline.org for Monthly Project Updates & Weekly Prayer Reminders.