Here is the latest news on the Building Project. Wow! There is no shortage of things to be diligently praying about......

Building Project Update
May 2008

The latest images...

Click on a picture to see a larger version. (Pictures are also available in the PDF version of this update.)

click to see a larger picture click to see a larger picture click to see a larger picture of the lower level floor plan click to see a larger picture of the main floor plan click to see a larger picture of the plaza walkway click to see a larger picture of the plaza walkway click to see a little bit larger picture of the lobby click to see a little bit larger version of the accent wall idea click to see a little bit larger picture of the sanctuary platform drawing

click to see a larger version of the plaza floor plan
Plaza

Bids are coming in...

We have received the formal bids for the building exterior and site improvements—and they are within budget. These bids represent more than 84% of the total construction cost. As you can see by the schedule below, we are now bidding out the Interior portion of the new building and expect to receive those bids back by May 23. The Interior phase represents about 16% of the construction cost. So, with bids coming in, construction estimates are now firming up as we continue to remain at the lower range of the estimated total project budget of $11.6 million.

Financing for the new "Worship Center"

Total Project Cost $11,600,000
Spent since Oct-07 585,000
Subtotal $11,015,000
Current Village Future Fund
(minus total project cost to date)
$ 2,378,019
Remaining Pledges left @ 75% $1,546,073
Total $7,090,908
Loan Amount Monthly Payment
Assuming Pledges @ 75%
(current giving rate)
$7,090,908 $44,000
Assuming Pledges @ 100%
(if all Villagers who made a commitment so far give 100%)
$4,348,873 $27,200

"Fast Facts"

The "Worship Center" will have three floors totaling 43,695 square feet:
Lower Level with 2 nurseries and a toddler care room and 3 multi-use classrooms;
Main Floor including a sanctuary with 800-1000 seats, baptismal, new piano and organ, 2 multi-use classrooms, an expandable lobby and lounge area with nearby coffee/tea bar and fireplace; and a
3rd Floor with over 10,000 square feet of unfinished expansion area for a future 300-seat balcony and additional classrooms.

There will also be an outdoor Plaza connecting the old and new buildings with covered walkways, water features, landscaping, benches, café tables and chairs.

Questions? Please contact Dale Himes, Project Manager (503-804-8911), Scott Moore, Business and Facilities Administrator (503-643-6511), Jim McGuire, Executive Pastor (503-643-6511), Dain Strobel, Communication Team Leader or any Staff and Elder Board member including: Mathew Abraham, Dan Crawford, Brian Forbes, Wayne Hart, Ron Henricksen, Sean Kim, Chong Lee, Scott Pelot, Scott Robinson, Doug Sauvageau, Wes Sealand and Tom Smith.

Dale