Weekly Prayer Reminder: 7-14-2008
For those of you unaware, we did obtain the Demo Permit last Tuesday with hand separation of the office wing occurring the next two days. The big track-hoe then took over on Friday morning and leveled the office wing in just about 2 hours. This week clean-up continues of the debris pile (in fact that work was done about 3:00 today), removal of the walk way canopy and clearing of the remaining plants and trees. Temporary weather protection of the exposed sanctuary building wall will also be completed this week. Finally, on Wednesday the Cedar Creek enhancement project will begin with the clearing of "non-native vegetation" —meaning blackberry bushes. Please keep in mind that the perimeter construction fencing will be adjusted as construction activities dictate.
Work Phases—completed tasks
- Demolition
- construction trailers arrive
- emergency service panels relocated
- office portables removed
- asbestos removed in ceiling, floor and windows
- natural gas pipes rerouted
- new electrical wire is pulled and outside panels set
- plumbing is capped
- Rita driveway and new connecting pathways are paved
- new gas meter installed
- new electrical transformer installed
- hand separation of office wing roof, floor and walls
- building demolition
- Sitework
- New Building Shell
- Plaza
- Existing Building Improvements
- New Building Interior Improvements