This week, work continues on excavation, stockpiling good soil, hauling off bad soil, compacting the good soil at the building pad, laying-out lower level foundation footings, installing new site utilities, digging the first elevator pit and stream restoration. Overall, permits are coming in on time and the project is tracking well. Construction crews are doing a very good job. If you visit Village during the week please thank the crews (Don, Chris, Dan, Leo, Wayne...) for their work.