Weekly Prayer Reminder: 9-29-2008
- Last Saturday and today, construction crews continued waterproofing the basement wall. They also completed installing steel rebar in the foundation footing forms.
- Tuesday, the plumbers are scheduled to complete the rough plumbing for the basement area.
- On Wednesday, more concrete footings will be poured. If the good weather holds, the basement level floor slab will be poured on Friday.
- Everyone is indeed thankful for the favorable weather over the last few weeks. It has had a positive effect on the project schedule and budget.
Dale Himes
Ecclesiastes 3:3b